| United States. Court of Claims - 1930 - 854 psl.
...sums may be waived in whole or in part in the discretion of the Secretary of the Interior. "Article 3. It is agreed that no claim shall accrue or charge...damage arising out of the nature of the work to be performed, or from any unforeseen or unusual difficulty that may be encountered in the prosecution... | |
| New York (State). Legislature. Senate - 1873 - 908 psl.
...will be replaced and retained on the work until these stipulations are faithfully fulfilled. 12. All loss or damage arising out of the nature of the work to be dene under this agreement, or from any unforeseen obstructions or difficulties which may be encountered... | |
| District of Columbia. Supreme Court (1863-1936), Arthur MacArthur (Sr.) - 1875 - 680 psl.
...and Gallaher, Loane & Co., is found the following provision : ''Sixth. It is further agreed that all loss or damage arising out of the nature of the work to be done under this agreement, or from any unforeseen obstruction or difficulties which may be encountered... | |
| 1884 - 784 psl.
...the Secretary of the Interior, the joints of the pipe to be perfectly secure and water-tight. 9. All loss or damage arising out of the nature of the work to be done, or from any unforeseen or unusual obstructions or difficulties which may be encountered in the prosecution of the... | |
| District of Columbia. Supreme Court (1863-1936), Franklin Hubbell Mackey - 1884 - 628 psl.
...force from the fact that in another portion of the contract there is a clause providing " that all loss or damage arising out of the nature of the work to b« done CONTRACTS (oontinued.) under this agreement, or from any unforeseen obstructions, or difficult... | |
| United States. Court of Claims - 1885 - 712 psl.
...repairs to be made by the board as they may deem, necessary. * * * " Sixth. It is further agreed that all loss or damage arising out of the nature of the work to be done under this agreement, or from any unforeseen obstruction or difficulties which may be encountered... | |
| 1921 - 1048 psl.
...properly adjusted to the work under this contract, making safe and easy approaches. » * « "21. All loss or damage arising out of the nature of the work to be done under this agreement, or from any unforeseen or unusual obstructions or diflicultios which may... | |
| 1889 - 1298 psl.
...contractors shall not be made until aft such certificate shall have been filed. THIRTEENTH. — All loss or damage arising out of the nature of the work to be done under this agreement, or from any unforeseen or unusual obstruction or difficulti« which may... | |
| William Rich Hutton - 1889 - 320 psl.
...Contractors shall not be made until after such certificate shall have been filed. THIRTEENTH. — All loss or damage arising out of the nature of the work to be done under this agreement, or from any unforeseen or unusual obstructions or difficulties which may... | |
| Edward Gurley Love - 1890 - 450 psl.
...this agreement. 11. Loss or Damage to be Sustained by Contractor. — It is further Agreed that all loss or damage arising out of the nature of the work to be done under this agreement, or from any unforseen obstructions or difficulties which may be encountered... | |
| |