INFORMATION AS TO STATUS OF THE SEVERAL PUBLIC BUILDINGS IN COURSE OF CONSTRUCTION OR AUTHORIZED, FOR WHICH ESTIMATES HAVE BEEN SUBMITTED IN THE REGULAR ANNUAL BOOK OF ESTIMATES AND IN HOUSE DOCUMENT NO. 1291, FOR APPROPRIATIONS FOR THE FISCAL YEAR 1912, FURNISHED BY THE SUPERVISING ARCHITECT, AS INDICATED IN THE FOREGOING LETTER FROM THE SECRETARY OF THE TREASURY.

[blocks in formation]

Drawings for this work will be taken up in the summer of 1911 and a contract probably be in force by January 1, 1912, and as the contract will have about six months to run, the amount estimated will be required.

[blocks in formation]

Drawings will be taken up in the summer of 1911 and a contract probably be in force by January 1, 1912. As this contract will have about six months to run, the estimated amount will be required.

[blocks in formation]

Drawings will be taken up about May, 1911, and a contract entered into by September, 1911. As this contract will have about nine months to run, the amount estimated will be required.

[blocks in formation]

This building is under contract to be completed in the spring of 1911. Entire amount required in 1911, and the $20,000 asked for in this bill should be appropriated in a deficiency bill of this session.

37

[blocks in formation]

Drawings are now under way and a contract will probably be in force by March, 1911, and the building completed by March, 1912. As building will be completed early in the calendar year 1912, the whole amount will be required.

[blocks in formation]

The drawings for this work were taken up in December, 1910, and a contract will probably be in force by May, 1911, and as this contract would have about 13 months to run, the amount estimated for will be required.

[blocks in formation]

This building is now under contract to be completed October 1, 1911. As it will be completed and occupied early in the fiscal year 1912, all this amount will be required.

ANNISTON, ALA. (COMPLETION).

Total authorization....

No appropriation.

No balance available.

Estimated in this bill.....

$3,200

3,200

This authorization is simply to complete small details in connection with building, the structure itself having been completed and occupied some time. The whole amount will be required.

[blocks in formation]

This building is under contract to be completed July 1, 1911. As it will be completed and occupied early in the fiscal year 1912, all this amount will be required.

[blocks in formation]

This building is under contract to be completed early in the fiscal year 1912, and therefore the entire amount will be required.

[blocks in formation]

This building is under contract to be completed early in the fiscal year 1912, and therefore this amount will be required.

[blocks in formation]

Drawings for this building will be taken up in March, 1911, and a contract will probably be in force in September, 1911. As this contract will have about eight months to run, the amount estimated will be required.

Total authorization....

AUBURN, N. Y. (COMPLETION).

No appropriation.
No balance available.
Estimated in this bill.....

$30,000

30,000

This authorization is for an extension to an old building. The drawings will be taken up about July 1, 1911, and a contract be in force by November, 1911. As the work is of a very simple character it will be completed prior to July, 1912, and the estimated amount will be required.

AUSTIN, TEX. (CONTINUATION).

Total authorization....

No appropriation.
No balance available.

Estimated in this bill....

$210,000

100,000

As this building is in a capital of a State, the department decided that it should be taken up at once, and in order to do so an appropriation of the amount estimated for will be required.

[blocks in formation]

This work is under advertisement and a contract will probably be in force by the spring of 1911. As this contract will have about 13 months to run, the amount estimated will be required.

[blocks in formation]

This work is under advertisement and a contract will probably be in force by February 1, 1911. As this is an extension and will not be a long operation after commencement, the amount asked for will be required.

BEAVER FALLS, PA. (COMPLETION).

Total authorization..

No appropriation.

No available balance. Estimated in this bill...

$5,000

5,000

As this is an extension of a very minor character the drawings will be taken up about July 1, 1911, and a contract no doubt will be in force by October and the work completed Fong prior to July, 1912. The whole amount estimated for will be required.

[blocks in formation]

This building is under contract to be completed April 1, 1911. As the contract expires in the spring of 1911, this amount will be required.

[blocks in formation]

The drawings for this work are well under way and a contract will probably be in force by March 1, 1911. As the contract will have over a year to run, the amount estimated for will be required.

[blocks in formation]

This building is under contract to be completed October 1, 1911. As it will be completed and occupied early in the fiscal year 1912, this entire amount will be required.

[blocks in formation]

The drawings for this work are well under way and a contract will be in force by March 1, 1911. As it will probably be completed early in the calendar year 1912, the amount estimated for will be required.

[blocks in formation]

The drawings for this work will be taken up about July 15, 1911, and a contract entered into about November 1, 1911. This amount will be required.

[blocks in formation]

The drawings for this work will be taken up in March, 1911, and a contract probably entered into by September, 1911, and therefore the amount asked for will be required.

[blocks in formation]

The drawings for this work will be taken up in April, 1911, and a contract probably entered into by October 1, 1911, and therefore it is believed that the amount asked for will be required.